NYC DOB Stop Work Order: Violations, Fines & What to Do
A Stop Work Order (SWO) is a directive from the New York City Department of Buildings (DOB) to immediately halt the construction, renovation, or demolition work covered by the order. If DOB posts one at your property, stop the affected work, tell the contractor and subcontractors, and read the notice to find out exactly what DOB has restricted.
Read the notice before anyone goes back to work
Start with the scope written on the posted order. A full Stop Work Order halts work at the site except for remedial work DOB authorizes to make it safe. A partial Stop Work Order halts the activity or area identified in the notice. Work outside that scope may continue only if it is otherwise lawful, properly permitted where required, and unaffected by any other order.
For example, an order limited to rear-yard excavation may leave unrelated interior work outside its scope. If the order is unclear or the crews share access or site protections, ask the issuing unit to clarify what can proceed before directing anyone to restart.
Common reasons for an order include work without a required permit, unsafe excavation or scaffolding, and work that departs from approved plans or violates building or zoning requirements. Photograph the posted notice and note the issue date, issuing unit, complaint or summons numbers shown, and the exact work or location listed. Keep the notice in place.
Need help with a NYC DOB Stop Work Order?
SLK Buildings can review the notice, related violations, and permit history, then help identify what DOB needs for rescission. Have the property address, a photo of the posted order, and any complaint or summons numbers ready.
On This Page
How to look up a NYC Stop Work Order
Search the DOB Stop Work Order Map for recent orders and rescissions. Open the map entry and follow its complaint number to see the record. The map covers the past two years. For older orders or a fuller property history, search Buildings Information System (BIS) or the DOB NOW Public Portal, as applicable.
Compare the online record with the notice at the site. If the record and notice differ, or the notice covers only part of the property and the scope is unclear, contact the issuing unit for confirmation.
What is the fine for violating a Stop Work Order?
Under NYC Administrative Code § 28-207.2.6, failing to comply with a Stop Work Order carries a DOB civil penalty of $6,000 for the initial violation and $12,000 for each subsequent violation. The law excepts work authorized by the commissioner to remedy an unsafe or hazardous condition.
- Failure to obey the order
- This DOB civil penalty applies when someone continues or allows work covered by an active order. DOB requires payment of assessed penalties for violating the order before rescission, subject to any applicable process under the code for a pending violation.
- Work without a permit
- The underlying unpermitted work can carry a separate civil penalty. See NYC work-without-permit civil penalties for how DOB calculates it.
- DOB-issued OATH summons
- A related summons can carry its own hearing, penalty, and correction requirements. Track it separately. See how to resolve an ECB/OATH violation.
If you receive both an order and a summons, calendar the hearing or response date while you address the order. Payment of a summons and DOB rescission are separate steps.
How to get a NYC DOB Stop Work Order lifted
- Identify why DOB issued the order. Match the notice to the complaint, inspection findings, related summonses, and applicable permits. Start with the unit listed on the order.
- Confirm the permitted corrective scope. Ask the issuing unit what work may take place under the order and what documentation DOB expects. Depending on the condition, you may need a licensed professional, revised drawings, or permits.
- Document the correction and address related requirements. Gather the permits, photos, or reports DOB requests. Submit a Certificate of Correction for related summonses when required, and address applicable civil penalties.
- Request the rescission inspection. Follow the issuing unit’s instructions for a reinspection and make the site and supporting records available. Use the DOB Stop Work Order guidance or the NYC311 construction safety inspection instructions to find the applicable appointment process.
- Confirm DOB has rescinded the order before restarting. Verify the rescission with the issuing unit and confirm the required permits cover the work you plan to resume.
For more on filings and enforcement, see the SLK Buildings guide to resolving a DOB Stop Work Order and the NYC DOB violations guide.
Common Stop Work Order questions
Can I restart as soon as DOB issues the permit?
Wait for DOB to rescind the order before restarting the affected work. If the order was issued for work without a permit, DOB requires the permit to be issued and the order to be rescinded.
What if I think the order was issued in error?
Keep the affected work paused and contact the issuing unit. Gather the notice, relevant approved plans and permits, and other evidence showing why the order may have been issued in error. NYC Administrative Code § 28-207.2.3 provides for rescission when DOB determines the order was issued in error or should not have been issued.
How long does it take to lift a Stop Work Order?
Timing depends on the reason for the order, the work or filings needed to correct it, any outstanding penalties or correction requirements, and the issuing unit’s inspection schedule. Ask the issuing unit which requirement is holding up rescission so you can address that item first.